Timeline plannerWill your lighting arrive
Will your lighting arrive
before your opening?
Custom decorative lighting lives on the critical path of every fit-out, and the question always comes too late. Enter your opening date: the planner walks the timeline backwards and tells you when your brief has to leave.
Your brief should leave
Verdict for today
Added. It will be waiting, pre-filled, in your sourcing request.
In short
A custom decorative lighting order typically needs 1 to 2 weeks for brief and written specification, 1 to 2 weeks for supplier quotes, 3 to 5 weeks for the sample loop, 12 to 20 weeks of production for custom pieces (8 to 12 for standard families), inspection inside the final production week, then 5 to 7 weeks of sea freight to Europe or 1 to 2 by air. Indicative planning ranges: they are confirmed per project at the quote stage.